Southeast Regional Director - Garry Lynn - Davis Field Airport (Muskogee)

January 2012    Southeast Region Report:

Ada     No new projects at this time.  Manager Is very pleased with winter weather so far!

Atoka     One new aircraft on the field. Working on the airport beacon. Fuel sales is steady. Looking forward to the conference.

Sallisaw   Waiting for a shipment of steel to arrive for the erection phase of a new hangar on the field. Two new based aircraft on the field in the last quarter. Aircraft detailing shop is busy .

Healdton   The City Manager advises that the airport expects to start the rehabilitation in April project start.  The contract has been awarded for this project.

 Ardmore   Business at both FBO’s is strong. Demolition completed on two buildings, and two more to be completed at a later date. Traffic has been steady.

Madill    Runway rehabilitation completed. Looking to acquire Airport Consultant. Working on removing some obstructions out of runway safety area. Future plans include extending runway to 3800 feet. *** Sent all info for Conference, suggests they will be attending.

Tishomingo Airpark  The airport is moving forward on a runway rehabilitation project.  

Muskogee    Bids for general contractor are out on new terminal building. Ground breaking hopefully in March.  Taxiway rehabilitation project expected to start in late summer.  All Hangars full and a waiting list started.

Southeast Regional Director - Garry Lynn, Davis Field Airport

********************************

October, 2011 Southeast Region Report:

Ada   Five jets on the fields, fuel receipts are steady. There is an active project on to update the Airport Master Plan. Ada received approval from the OAC for a grant up to $500,000.00 with matching funds from the city. Possibly some new hangars to be built at the airport in the very near future.

Atoka    A new airport beacon has been installed and partial new security fencing erected. The apron is being enlarged to accommodate 3 new hangars.  These new hangars are to be leased by 3 new customers. In 2013 the City of Atoka will widen the runway from 40 feet to sixty feet.

Sallisaw   The airport is working on some drainage issues. The potential for several new hangar leases are in the works.

Healdton   The City Manager advises that the airport is about 6 weeks from a runway rehabilitation project start.  They will be changing the runway surface from grass to asphalt. The manager also requested a membership package for OAOA .

Madill    Runway rehabilitation completed. Looking to acquire Airport Consultant. Working on removing some obstructions out of runway safety area. Future plans include extending runway to 3800 feet.

Tishomingo Airpark  The airport has just been awarded a $750,000 grant  with matching funds from local tribal funds to do a runway rehabilitation. Future plans include building several hangars and maybe self serve fuel. 

    ******************************************

July 24, 2009 Report:

Broken Bow -- no new projects.

Wilburton - Manager John Hart reports that the airport would like to participate in projects with the FAA and the OAC.  The current needs include runway lights.

Ardmore Municipal -  Chris Bryant is the manager.  Chris is very intersted in being an active part of OAOA.  The runway extension for runway 17/35 is nearly complete.  As we would all confess, Chris says that he needs more money. 

Ada Municipal - Terry Hall reports that the taxiway reconstruction and realignment project is nearly complete.  This project includes new taxiway lights and the first LED signs in the state.  The City has contracted with Heartland Aviation as the temporary FBO.   This year's Ada Air Expo was very successful.

Chris Bryant, Southeast Regional Director, Ardmore Municipal Airport